How to Test Obstruction Detection and Reversal on a Speed Gate

For North American integrators: a four-step record for speed gate obstruction testing—trigger, stop or reverse, clear, and reset—with test methods defined by project documents.

BMT Smart Editorial

On a North American speed gate commissioning site, integrators often need to demonstrate to the owner that when an obstruction appears in the lane, the gate stops or reverses and then returns to normal operation after the obstruction is removed. This judgment cannot rely on a quick feel test. It should be broken into four recordable steps: trigger, stop or reverse, obstruction cleared, and reset to passage. The test piece, position, trigger conditions, and measured values for each step should be defined by the test method adopted for the project. The BS EN 17352:2022 standard record describes safety in use requirements and test methods for power operated pedestrian entrance control equipment, but the standard itself does not replace project acceptance documents; specific thresholds require the project documentation.

Step 1: Confirm trigger conditions and test piece

Trigger conditions include the size, material, entry position, and movement speed of the obstruction. The project test method should specify the test piece (for example, a rod or block of defined diameter and stiffness) and from which direction and at which segment of the gate leaf travel it is introduced. Integrators should perform the test in a controlled environment, by trained personnel following the gate manual and approved procedures, and should not substitute body parts or improvised objects for the specified test piece. Records should state the test piece specification, introduction position, and gate leaf movement direction.

Step 2: Record stop or reverse behaviour

After the obstruction triggers, the gate leaf may stop, reverse open, or reverse close, depending on the gate design, gate controller logic, and leaf position. The acceptance record should separately note whether the leaf stopped, the stop position, whether reverse motion occurred, the reverse travel distance, and the response from trigger to action. These observations should be compared with the anti-crush logic described in the gate manual, not judged simply as pass or fail by on-site impression. If the manual requires specific fault codes or indicator states, these should also be recorded.

Step 3: Clear the obstruction and confirm state

After removing the test piece, confirm whether the gate leaf remains in the stopped or reversed position, whether the gate controller indicates a reset-pending state, and whether any fault indication requires manual acknowledgement. At this point, do not force the leaf by hand; follow the reset method specified in the gate manual. Record the time the obstruction was cleared, the leaf state, and the controller indication as preconditions for the reset-to-passage step.

Step 4: Reset to passage and close the record

In the reset-to-passage step, use a valid access grant signal to trigger one normal passage, observe whether the leaf completes a full open-close cycle, and confirm the gate returns to a state ready to accept the next authorisation. Record the source of the access grant (reader, push button, or access control system), the leaf action, and the final state. The four-step record should form a closed loop: trigger condition, stop or reverse behaviour, obstruction-cleared state, and reset passage result, each with a verifiable observation. In this way, the acceptance record submitted by the integrator can be mapped to specific clauses of the project test method rather than a general statement that anti-crush is normal.

Responsibility levels should be stated: the mechanism supplier (such as the swing gate mechanism families listed in the BMT product centre) provides the drive assembly; the gate controller logic and access control authorisation are configured by the gate manufacturer or system integrator; and the overall safety performance is based on measured results under the corresponding conditions. The BMT product centre page shows mechanism families and models only and does not constitute a statement of overall anti-crush performance or project acceptance results.