Engineering Blog / Commissioning & maintenance
What Should a Pedestrian Gate Do After Power Is Restored?
Build test cases around power-loss timing, barrier position, and recovery steps—recording barrier homing, fault clearing, whether old grants expire, and how normal passage resumes.
For a pedestrian gate acceptance test, write down what the barrier should do when power returns, what happens to a pending grant and who clears the lane for service. Run the sequence with the lane out of service under the manufacturer’s approved procedure.
Three variables every test case should cover
Build each case around the point of power loss, the barrier position and the expected response when power returns. Agree in advance whether the specified configuration releases or holds the barrier, how it treats a pending grant, and which conditions require a manual reset.
| Power-loss timing | Barrier position · Reference | Behaviour to record |
|---|---|---|
| Before passage (standby) | Closed · Project rules, controller manual | Does barrier stay closed after power restoration; are faults cleared |
| During passage (after grant) | Mid-travel or open · Project rules, access panel configuration | How barrier homes after restoration; whether old grant remains valid |
| After passage (closed) | Closed · Controller manual, commissioning log | Does normal standby resume; any abnormal alarms |
Substitute the approved lane configuration for each example in the table. Use the mechanism version, gate controller logic, access panel configuration and manufacturer documents to define the expected result. Use the BMT Smart mechanism catalogue to identify the drive version.
What exactly should be recorded on power restoration?
Record the observed barrier position, controller fault status, treatment of the earlier grant and how passage resumed. Give each observation a pass criterion from the approved design. Where the panel provides an event log, preserve the entries before and after the test so they can be aligned with the gate’s state. For a project using an A1610, refer to the Axis A1610 door controller documentation for its event log.
- What behaviour should be recorded on power restoration?
- Record barrier homing, fault clearing, whether old grants expire per project rules, and how normal passage resumes. Each item should have a clear criterion and be checked against project rules and supplier manuals.
Responsibility layers and record ownership
Assign each observation to the equipment that reports it. The access panel provides grant history, the gate controller reports startup and fault status, and the physical observation records where the barrier stopped. Tie the records together with a test case ID and timestamp.
- Before testing, confirm project rules with both access and gate parties: power-loss release method, old-grant expiry rule, and reset requirements after restoration.
- Design at least three test cases by power-loss timing and barrier position, covering standby, during passage, and after passage.
- For each case, record barrier position, controller status, access log, and passage recovery method, with pass/fail criteria.
- On abnormality, troubleshoot by layer: access grant records first, then gate controller status, then mechanism.
- File records into commissioning documentation after testing; they do not replace the full unit acceptance procedure.
Keep the completed record, event logs and applicable supplier documents with the commissioning file for the lane.