Engineering Blog / Commissioning & maintenance
How to test fare gate throughput during peak entry
Count completed passages within an agreed test window and log how rejected reads, assistance and lane availability affect the result.
Decide what you are measuring before the peak period begins. A station operator may need throughput for a bank of lanes, while an equipment acceptance test may call for a single lane in a fixed configuration. Record which lanes are open, the test direction and how your team will count a completed passage.
Capture the events behind the count
- Log successful passages and the observation window.
- Log re-taps, rejected reads and staff-assisted passage separately.
- Record temporary lane closures and the queue at the start and end of the test.
Report completed passages per minute for the stated window, alongside the number of operational lanes and any interruptions. If the team also measures opening time, report it as a separate equipment measure. The Beijing Chaoyang station update describes equipment additions by entrance. An acceptance test would add observed passage and queue data for the agreed conditions.