Take three separate measurements when surveying an existing fare gate lane: the usable opening, equipment footprint and service envelope.

BMT Smart Editorial

Start at the point a rider actually passes through. Put the leaves in the normal fully open position under the agency’s approved procedure. Measure the narrowest usable opening and note any part that projects into it, including a leaf edge, post or adjacent railing.

Put three dimensions on the site plan

DimensionWhat to mark
Clear openingThe limiting surfaces and measurement location with the leaves open.
Equipment footprintThe cabinet and base outlines measured from the site datum.
Service envelopeRoom for covers, access panels, cabling and removal of the drive.

Compare the marked-up plan with the agency’s criteria and the approved drawing. If the layout changes on either side of the lane, recheck the complete route and record where the smallest opening occurs. BART’s rider guide is one example of an operator identifying wider fare gates as a separate facility feature. Use the governing requirements and drawings for the actual site. The Suzhou Metro Line 5 gate service update also describes staff-assisted access, a separate operating condition to record in a retrofit survey.